Western Shoreline Virtual Town Hall Meeting
Lakeside is continuing to make progress on the western shoreline and is hosting a virtual Town Hall Meeting on Friday, Nov. 6 at 6 p.m. To participate, complete the RSVP link. A Zoom link will be emailed 24 hours prior to the meeting.
KS Associates, located in Elyria, Ohio, continues to be the project lead. Work will start in spring 2024. An update about the project and the next steps will be provided by a representative of KS Associates, Lakeside Interim President & CEO Charles Allen, and Historic Design Review Board & Development Manager Jim Switzer.
The plan is first to place toe stone (large in the water stone) embedded two feet into the lakebed. The large toe stone will help dissipate the waves and energy along this location. New armor stone will be placed along the slope of the existing revetment on top of the toe stone. This will prevent long-term erosion along the western shoreline.